Position:HomeAchievementGrid-tied Solar Power Project

Grid-tied Solar Power Project

Baoshan iron & steel 50 MWP roof photovoltaic (pv) grid project

Date:2015-03-17Source:未知Views:times

Baosteel gold sun demonstration projects for the 2012, the total installed capacity of 50 MWp. It is installed in the premises of baosteel, hot and cold rolled silicon steel 13 production unit on the roof, such as the user side 10 KV interconnection. After the completion of expected power generating capacity of 50 million degrees, all spontaneous for private use. saving Coal 20000 tons, 52000 tons of CO2 emissions, 440 tons of SO2, NOx, 200 tons, 340 tons of dust, economic and social environment benefit is remarkable. The project invested by Beijing guo fa hua qi energy saving technology co., LTD., in accordance with the contract energy management mode of operation. CCE oasis wins warm walzwerk, treasure, car plate factory MWp EPC contractor.