Grid-tied Solar Power Project

Lianxing New Energy (Phase 1) Ground-based Solar PV Power Plant Project in Xinjiang Tulufan

Date:2013-06-26Source:未知Views:times

The Xinjiang Lianxing New Energy project with total installed capacity 20MW is a ground-based project in China, located in the gobi desset which is 15km from northeast of Tulufan cityDatong. It adopts polycrystalline modules and fixed angle installation, and connects 220KV to the grid. After the project is completed, it is estimated that it will generate 27.6 million KWH annually.

CECEP Oasis invested this project with total 0.4 billion RMB. The offtaker Xinjiang Lianxing New Energy Co.,Ltd took the project and managed the project operation. CECEP Oasis is the EPC contractor and the project is estimated to complete the grid connection in May 2013.